Warning Time

The gap between a system knowing and a system telling.

Claim ledger

The Warning Was Slower Than the Water · atom WT-001 preprint — not peer reviewed

Claim ledger — The Warning Was Slower Than the Water

Atom WT-001 · ledger version 16 claims · generated 2026-09-15

Every number spoken or shown in this piece appears below with what kind of number it is and where it came from. If one of them is wrong, tell me and the correction gets published with a date.

Type means:

Source status: preprint-unreviewed · DOI 10.31223/X5HN5H

id claim type source retrieved
C01 The ice-rock mass detached from the northern flank of the Langtang massif at 08:37:10 Nepal Time on 26 August 2026 reported · abstract Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C02 The mass public alert followed the trigger by 38.8 minutes calculated · abstract Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C03 The wave reached the uppermost gauge within 12.8 minutes of the trigger calculated · abstract Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C04 Lead time at the first inhabited settlement was -26 to -16 minutes calculated · abstract Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C05 Lead time at the next settlement downstream was +4 to +14 minutes calculated · abstract Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C06 Three destroyed gauges never triggered threshold alerts, having been lost at 27, 69 and 87 percent of their own warning stage observed Acharya, S. (2026), EarthArXiv preprint, v5; DHM Flood Forecasting Division station records 2026-09-12
C07 The USGS reclassified the signal from a magnitude 4.4 earthquake to a magnitude 5.2 landslide; long-period seismic waves were generated by the collapse rather than preceding it reported · event page, reviewed solution; FDSN web service USGS Earthquake Hazards Program, reviewed solution for event us7000tbwb (type: landslide, mag 5.2 ms_vx) 2026-09-13
C08 Initial seismic estimates put the detached mass between 197 and 492 million cubic metres modeled · catalogue entry GFZ GEOFON catalogue solution gfz2026qrfy (Mw 5.7, depth 0, type landslide); inversion estimates circulated by GFZ Potsdam and D. Shugar 2026-09-13
C09 A block of bedrock and glacier ice roughly 600 metres wide fell about 1,200 vertical metres from an elevation of 5,200 to 5,400 metres reported · press release; corroborated in graded dossier section 2 ICIMOD press release and field/remote-sensing assessment, 26 Aug 2026; glaciological commentary (Petley/Eos, Davies/AntarcticGlaciers) for the geometry range 2026-09-13
C10 This was not a glacial lake outburst flood. ICIMOD and Nepal's Department of Hydrology and Meteorology considered a GLOF and ruled it out, describing a four-stage chain - rock and ice avalanche, temporary natural dam across the Lhende Khola, sudden dam break, debris flow reported · press release; sitrep mirrored at nirajbhusal.github.io/rasuwa-flood-bulletin/ ICIMOD press release, 26 Aug 2026; DHM Flood Forecasting Division technical situation report (Bhadra 10), section 2 2026-09-13
C11 679,295 warning text messages were dispatched, within about a minute of the alert being issued observed · sitrep section 5; no permanent official URL exists, contemporaneous reproductions agree on every figure DHM Flood Forecasting Division technical situation report (Bhadra 10), section 5: SMS dispatch 09:16 NPT, 679,295 messages (Nepal Telecom 435,635; Ncell remainder) 2026-09-13
C12 The District Administration Office and Betrawati station staff notified the Flood Forecasting Division at 09:00; the alert was confirmed at 09:15 and SMS dispatch began at 09:16 observed · sitrep section 2 DHM Flood Forecasting Division technical situation report (Bhadra 10), section 2: notification chronology 2026-09-13
C13 Confirmed deaths stand at 1,386 in Nepal as of 12 September and 43 in the Tibet Autonomous Region as of 6 September, with 5,130 and 519 missing respectively reported Nepal Ministry of Home Affairs / NDRRMA figures via wire reporting, 12 Sep 2026; Tibet AR authorities via Xinhua, 6 Sep 2026 2026-09-13
C14 The flood struck settlements along a 72 kilometre stretch of the Trishuli River reported Acharya, S. (2026), EarthArXiv preprint, v5 2026-09-12
C15 The early-warning system was optimised for monsoon and perennial flooding, and the upstream monitoring stations were swept away before alerts could be sent reported · sitrep sections 2 and 4 DHM Flood Forecasting Division technical situation report (Bhadra 10), sections 2 and 4: station losses and thresholds; interpretation of the design mismatch is the preprint's own 2026-09-13
C16 Thirteen hydropower projects were damaged, removing 431 megawatts from the grid reported · article, NEA preliminary study Nepal Electricity Authority preliminary damage assessment, reported by the Kathmandu Post, 30 Aug 2026 2026-09-13

Contested

Corrections

None yet.